Pricing & Estimating 10 min read • Aug 28, 2026

Inground Gunite Pool Construction: Excavation, Plumbing, Coping & Cost

2026 pricing and phase-by-phase contractor guide for inground gunite pool installation in Texas. Excavation, steel rebar grid, pneumatic gunite shoots, coping, and plaster finishes.

Building an inground gunite swimming pool in Texas requires engineered reinforcement to handle intense soil shear, thermal expansion, and torrential weather.

Phase-by-Phase Gunite Pool Construction Milestones

PhaseWork DescriptionDurationCritical Inspection
Phase 1: Dig & SteelExcavation, grading, box layout & #4 rebar cage grid3 – 6 DaysCity steel & bonding inspection
Phase 2: Rough PlumbingSchedule 40 PVC returns, suction mains, spa jets & manifolds2 – 3 DaysPlumbing pressure test (35+ PSI)
Phase 3: Gunite ShootPneumatic dry-mix concrete application (4,000+ PSI shell)1 – 2 DaysWatering cure (2x daily for 14 days)
Phase 4: Coping & TileNatural travertine or limestone coping + 6" waterline tile1 – 2 WeeksBonding & level checks
Phase 5: Decking & EquipmentSurrounding patio pour, pumps, cartridge filter & salt system1 – 2 WeeksElectric final & bonding grid
Phase 6: Plaster & FillPebble / quartz interior finish, acid wash, immediate water fill2 – 3 DaysPool startup & chemical balancing

Equipment Selection for Texas Summers

Equip pools with variable-speed pumps (Pentair IntelliFlo or Hayward TriStar) for significant energy efficiency, oversized cartridge filters (420 to 520 sq ft) to handle spring pollen and summer dust, and salt-chlorine generators to eliminate harsh chlorine odor and skin irritation.

Frequently Asked Questions

How much does an inground gunite pool cost in Texas in 2026?

A standard custom gunite swimming pool (approx. 75 to 85 perimeter feet, 14x28 to 16x32) in Texas costs $65,000 to $95,000. Adding an attached raised spa, travertine coping, heater, automation, and LED lighting brings the investment to $90,000 to $145,000+.

How long does it take to build a gunite pool in Texas?

Standard construction takes 8 to 14 weeks from dig day to water fill, assuming clear weather and municipal permit approvals (digging: 2 days, steel & plumbing: 1 week, gunite shoot & 28-day cure, tile/coping: 1-2 weeks, decking: 1 week, plaster & fill: 3 days).

Is gunite better than fiberglass in Texas clay soils?

Gunite provides superior structural customizability and anchoring in shifting Texas clays when engineered with a dense #4 rebar cage on 8 to 10-inch centers and perimeter bond beams.