Managing vacancy loss across large Texas multi-family portfolios demands rigorous make-ready scheduling, trusted multi-trade punch crews, and standardized replacement specifications.
Standard 5-Day Apartment Make-Ready Sequence
| Turn Day | Trade Contractor Scope | Verification Milestone |
|---|---|---|
| Day 1: Trash-Out & MEP Punch | Remove abandoned property, test all plumbing stops, outlets, HVAC delta-T | Maintenance intake sign-off |
| Day 2: Drywall Patch & Full Paint | Spackle nail holes, repair drywall dings, spray ceilings and walls (eggshell/satin) | Drywall smooth check |
| Day 3: Flooring Repair / Swap | LVP replacement or professional carpet steam-cleaning / pad replacement | Floor seam & transition check |
| Day 4: Tub/Counter Glaze & Hardware | Resurface bathtub, replace cabinet pulls, install new kitchen/bath faucet aerators | Plumbing drain test |
| Day 5: Deep Detail Clean & Key Re-Pin | Appliance interior scrub, window track vacuum, install new smart lock cylinder | Property manager final walk |
Standardized Paint & Hardware Specs
Successful management companies standardize on one wall color (e.g., Sherwin-Williams Agreeable Gray or Repose Gray) across an entire asset to eliminate paint color matching errors and expedite quick touch-ups.